SD

"Steve DeMars"

01/08/2005 8:31 PM

Concrete - How thin can I go . . .

I have a garage, 17' X 20' inside area. It is a converted carport . . .
There lies the problem . . . The carport was poured with a "hump" in the
middle running across the 20'. This was so the rain blowing in from front
are rear would drain. Well now I have decided to make this area into my
shop, I have a problem. I want it to be level. In the center the thickest I
can pour is 1.5". Any thicker and it creates all sorts of problems, like
doors not opening. As I go down the slopes it will get to be about 3.5"
thick. The existing sloped slab is over 20 years old with no cracks.
I have been told that if I pour it this way, it will crack . . . Any
suggestions appreciated . . .


This topic has 13 replies

Dd

"Doug"

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 4:37 AM

I poured a slab in my garage last summer, mine is about 5" thick at a
minimum. From the research I did, 1 1/2" is pushing it, and I would be
hesitant to go that thin. Can you maintain some of that pitch, and
give yourself and extra inch in the high spot? You'd probably never
notice such a slight pitch in the floor, it would also give you some
drain pitch (might not be necessary) I pitched mine toward the garage
doors. Also, I'd suggest you get fiber reinforced concrete.

rh

"robo hippy"

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 8:33 AM

If you tear out the old floor, and replace it, 4 inch thick is fine,
more than that is over kill. Rather than the mesh, go with #4 (1/2
inch) rebar about 24 to 30 inch on center. Mesh is a royal PITA, and
only works if it is suspended in the center of the slab which is almost
impossible to do unless you use the heavy sheets of it rather than the
rolls. The fibermesh works well in helping to prevent cracks. By
varying the thickness of the slab from 1 1/2 inches to 3 1/2 inches you
can guarantee cracking. If you want concrete for a floor, replacing
would be the best choice. Putting in a wood floor would be a good
alternative for your feet and back. You could also shim the machines
and benches to keep them level, and work with the uneven floor rather
than replace it.
robo hippy

m

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 5:58 PM

You need to get the floor perfectly clean to start.

A few key holes to help the new surface lock in may be good.

You want to do it in sections. Leave the middle hump until last
(thinnest section)

There are newer patching materials for concrete that can go to 1/2"
with no problems but surface preparation is essential.

The cheapest method if you can do the work is to chip out the hump.

Note: If the slab has a foundation at the edges you do NOT want to
break up the slab.

Consult a concrete worker in your area,

Ee

"EXT"

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

01/08/2005 11:15 PM

I have done it down to less than an inch and it works but I have a special
procedure to ensure that it is bonded to the old concrete.

"Steve DeMars" <[email protected]> wrote in message
news:Q0AHe.4216$mu6.3085@okepread04...
> I have a garage, 17' X 20' inside area. It is a converted carport . . .
> There lies the problem . . . The carport was poured with a "hump" in the
> middle running across the 20'. This was so the rain blowing in from front
> are rear would drain. Well now I have decided to make this area into my
> shop, I have a problem. I want it to be level. In the center the thickest
I
> can pour is 1.5". Any thicker and it creates all sorts of problems, like
> doors not opening. As I go down the slopes it will get to be about 3.5"
> thick. The existing sloped slab is over 20 years old with no cracks.
> I have been told that if I pour it this way, it will crack . . . Any
> suggestions appreciated . . .
>
>

Bb

Bruce

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 5:25 PM

On Tue, 2 Aug 2005 06:44:18 -0600, Guess who wrote
(in article <[email protected]>):

> On Tue, 02 Aug 2005 04:26:21 GMT, Lew Hodgett
> <[email protected]> wrote:
>
>> Don't be surprised if jack hammering out the existing crowned pad and
>> pouring a whole new, mesh reinforced pad doesn't turn out to be the
>> least expense way to do the job.
>
> That was my first thought, but also because once done, the floor can
> be whatever reasonable thickness is required without the variation
> otherwise. I didn't suggest it since I thought the OP might object,
> so offered the other alternative of a bonding material. So, I'd go
> along with you that this is the best approach in the long run.
>
> So, rent a jack-hammer and go for it. You might have to rent somebody
> to use the hammer, but again you can do that and then get on with what
> you really want to do, your woodworking.
>

If you pour over the existing slab with the dimensions you stated you'll need
to use a latex additive in the concrete along with the bonding agent.
Basically you need to mix up a giant batch of tile thin-set.

The only sure way to make it work is with the jack hammer.....

-Bruce

LH

Lew Hodgett

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 4:26 AM

An update.

I previously wrote:

> RE: Subject
>
> A 4" layer of concrete is considered little more than a dust cover.
>
> If you want to do it to last, think at least 6" with mesh.


Don't be surprised if jack hammering out the existing crowned pad and
pouring a whole new, mesh reinforced pad doesn't turn out to be the
least expense way to do the job.

Lew

Jm

"J"

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 3:28 PM

Talk to a concrete guy about levelling the slab. There are compounds which
can be poured on top of a concrete slab to level it and can be as thin as a
few millimeters. They can just put in a perimeter form and fill it up until
the hump is covered. It is more $ than ordinary concrete, but if your
existing slab is sound then it would be dumb to remove and replace it.

-j


"Steve DeMars" <[email protected]> wrote in message
news:Q0AHe.4216$mu6.3085@okepread04...
> I have a garage, 17' X 20' inside area. It is a converted carport . . .
> There lies the problem . . . The carport was poured with a "hump" in the
> middle running across the 20'. This was so the rain blowing in from front
> are rear would drain. Well now I have decided to make this area into my
> shop, I have a problem. I want it to be level. In the center the thickest
I
> can pour is 1.5". Any thicker and it creates all sorts of problems, like
> doors not opening. As I go down the slopes it will get to be about 3.5"
> thick. The existing sloped slab is over 20 years old with no cracks.
> I have been told that if I pour it this way, it will crack . . . Any
> suggestions appreciated . . .
>
>

Gw

Guess who

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 8:44 AM

On Tue, 02 Aug 2005 04:26:21 GMT, Lew Hodgett
<[email protected]> wrote:

>Don't be surprised if jack hammering out the existing crowned pad and
>pouring a whole new, mesh reinforced pad doesn't turn out to be the
>least expense way to do the job.

That was my first thought, but also because once done, the floor can
be whatever reasonable thickness is required without the variation
otherwise. I didn't suggest it since I thought the OP might object,
so offered the other alternative of a bonding material. So, I'd go
along with you that this is the best approach in the long run.

So, rent a jack-hammer and go for it. You might have to rent somebody
to use the hammer, but again you can do that and then get on with what
you really want to do, your woodworking.

BG

Bob G.

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 7:17 AM

>
>Do you realy want a "destroy-any-edge-that-falls-on-it" floor in your
>workshop? Consider a wooden or OSB floor shimmed level over the concrete.

==========
To convert a carport into a shop I have to agree.... I would much
prefer to be standing on a wood floor all day then a concrete floor...

Can't remember the last time I dropped a chisel however...I just know
my legs will feel better at the end of the day...

Bob Griffiths

Gw

Guess who

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

01/08/2005 10:51 PM

On Mon, 1 Aug 2005 20:31:02 -0500, "Steve DeMars"
<[email protected]> wrote:

>I have a garage, 17' X 20' inside area. It is a converted carport . . .
>There lies the problem . . . The carport was poured with a "hump" in the
>middle running across the 20'. This was so the rain blowing in from front
>are rear would drain. Well now I have decided to make this area into my
>shop, I have a problem. I want it to be level.

http://www.quikrete.com/catalog/ConcreteBondingAdhesive.html

Pn

Prometheus

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 8:17 PM

On Tue, 02 Aug 2005 08:44:18 -0400, Guess who
<[email protected]> wrote:

>On Tue, 02 Aug 2005 04:26:21 GMT, Lew Hodgett
><[email protected]> wrote:
>
>>Don't be surprised if jack hammering out the existing crowned pad and
>>pouring a whole new, mesh reinforced pad doesn't turn out to be the
>>least expense way to do the job.
>
>That was my first thought, but also because once done, the floor can
>be whatever reasonable thickness is required without the variation
>otherwise. I didn't suggest it since I thought the OP might object,
>so offered the other alternative of a bonding material. So, I'd go
>along with you that this is the best approach in the long run.
>
>So, rent a jack-hammer and go for it. You might have to rent somebody
>to use the hammer, but again you can do that and then get on with what
>you really want to do, your woodworking.

Not too hard for a do-it-yourself job, provided you care to take the
time. If you get the old slab out, it'd be a whole lot less expensive
to have someone come in and pour a new one for you.

Just got done taking out a bunch of concrete that had been installed
by a freeway contractor, and that stuff was tough (8" slab with 3/4"
thick rebar every 14 inches or so- talk about overkill for a
driveway!). Took a day to remove about a garage's worth of slab- the
guys I work with said it usually takes an hour or two with a normal
driveway, but this one was an irritating exception! Used a Bosch
"Brute" hammer, and it worked like a charm- wasn't even sore the next
day. Make sure you've got a prybar and some good leather gloves to
get the concrete out, though. FWIW, I've never used a jackhammer
before Monday (always did it the hard way with a masonry chisel and a
sledge in the past), and it's about as simple as it gets.

LH

Lew Hodgett

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 3:31 AM

RE: Subject

A 4" layer of concrete is considered little more than a dust cover.

If you want to do it to last, think at least 6" with mesh.

Lew

JH

Juergen Hannappel

in reply to "Steve DeMars" on 01/08/2005 8:31 PM

02/08/2005 9:30 AM

"Steve DeMars" <[email protected]> writes:

> I have a garage, 17' X 20' inside area. It is a converted carport . . .
> There lies the problem . . . The carport was poured with a "hump" in the
> middle running across the 20'. This was so the rain blowing in from front

Do you realy want a "destroy-any-edge-that-falls-on-it" floor in your
workshop? Consider a wooden or OSB floor shimmed level over the concrete.

--
Dr. Juergen Hannappel http://lisa2.physik.uni-bonn.de/~hannappe
mailto:[email protected] Phone: +49 228 73 2447 FAX ... 7869
Physikalisches Institut der Uni Bonn Nussallee 12, D-53115 Bonn, Germany
CERN: Phone: +412276 76461 Fax: ..77930 Bat. 892-R-A13 CH-1211 Geneve 23


You’ve reached the end of replies